  Minutes of meeting

  For

  project

  In

  South sumatera,indonesia

  Attendance:Refer to Attached List(see Attachment 1)

  Date : October 19, 2009

  Place :Hangzhou

  1. introduction

  The agreed agenda are as follows:

  A. Coal supply issue

  B. POA for signing MOU regarding the HVDC Sumatera-Java transmission Project

  C. Financial Advisor Mandate letter

  D. How to push forward the power plant,coal mine and transmission projects.

  2. The result of the meeting:

  General overview: All the shareholders have the same understanding that even if the project didn’t make expected progress in the past several months due to the HVDC T/L issues and the influence of the new Minning Law to coal supply scheme, all the attendees still have confidence that all these issues will be solved with the best efforts of all parties.

  Coal Supply issue

  PTBA made a comprehensive meaningful presentation regarding the new mining law, its impact to signed JVC Coal Mine and PTBA opinion for new coalsupply scheme as well as response to CDB letter of 11 August 2009.

  The summary of PTBA’s proposal scheme in its presentation is as follows:

  1 PTBA cannot assign its right and obligation as mining permits holder to other party pursuant to the new mining law.

  2 it is PTBA as mining permit holder who shall decide the coal price, hence, the revenues account shall be reckoned in PTBA’s book.(which may affect to royalty,tax,etc)

  3coal supply agreement shall be established between JVC power and PTBA.

  4 PTBA cannot fulfill the requirement of CDB that the KP is held by PTBA’s subsidiary due to an uncertainty of getting KP by PTBA or its subsidiary.

  5 as long as PTBA holds the mining permit and hold a full authority of the mine then PTBA can give a guaranty of coal supply to JVC Power.

  The attendees discussed the proposed scheme made by PTBA as follows:

  PTBA concludes, base on all input from received information, the followings 4 possible coal supply schemes that comply with the new mining law:

  1 Pass-through scheme(scheme 1)

  2 PTBA as the coal supplier(scheme 2)

  3 JVC Coal Mine will be coal mining service company or other position(scheme 3)

相关文章

公司年终工作总结表彰大会方案2023-06-04 01:57:13

扶贫日宣传活动专题会议简报2023-06-10 05:26:04

实用的会议通知汇总六篇2023-06-10 12:37:55

评审会议纪要怎么写2023-06-08 00:03:07

入队仪式老队员代表讲话2023-06-05 15:32:00

全省国税工作会议讲话2023-06-07 16:22:45

上海对外经贸大学和北京交通大学(威海校区)对比哪个好(排名分数线区2024-03-31 16:25:18

河北高考排名237950名物理能上什么大学(能报哪些学校)2024-03-31 16:19:23

山东城市建设职业学院在山东招生人数和招生计划 多少人2024-03-31 16:15:16

上海农林职业技术学院在湖南招生人数和招生计划 多少人2024-03-31 16:12:52

吉林农业科技学院在湖南招生人数和招生计划 多少人2024-03-31 16:09:19

安徽高考多少分可以上云南经贸外事职业学院 招生人数和最低分2024-03-31 16:04:52

学生会会议纪要2023-06-12 23:57:41

万能版秋季运动会闭幕词范文2023-06-19 11:40:54

旅游产业发展座谈会议简报2023-06-05 22:19:53